This page last changed on Sep 20, 2004 by scytacki.
Task Ann Scott 50% Stephen 50% Planned Start Planned Finish Actual Start Actual Finish
evaluate ozone   1 wk   Jul 5 Jul 9 Jul 15 Jul 20
Syncing Design   2 days   Jul 20 Jul 28 Jul 20  
Syncing Milestones   4 wk   Jul 29 Aug 20    
break while finishing vendor integration              
Java 1.4 version 1   1 mo   Oct 11 Nov 5    
Waba version 1   1 mo   Nov 5 Dec 3    
Palm Syncing   1 mo   Dec 6 Jan 7 2005    